Townwide Paving Improvements Schedule

The following is a schedule submitted by the Townwide Paving Contractor P. J. Albert.  Please be advised that this proposed schedule is the Contractors best estimate as to the dates when this work will be occurring.  Please bear in mind that changes to this schedule may occur suddenly as a result of supply issues, weather or other reasons.  Please be advised around these dates there may be traffic delays or detours that are imposed.  Thank you for your cooperation.

Paxton Rd
8/9 Tuesday: Start raise castings
8/10 Wednesday: Start Driveway Work
8/11 Thursday: Continue Driveway Work
8/12 Friday: Binder in Driveways as needed
8/17 Wednesday: Start top Northwest Rd or Paxton Rd if structures are done and its ready for top
8/18 Thursday: Complete top on Northwest Rd or Paxton Rd if ready.

Gold Nugget Rd
8/8 Monday: Grade and Reclaim
8/9 Tuesday: Grade and Reclaim
8/15 Monday: Pave Binder

Brown St, Duggan St & Pope St
8/9 Tuesday: Lower and plate structure,  Start Reclaim
8/10 Wednesday: Continue Grade and Reclaim, Excavate Sidewalk
8/11 Thursday: Finish Grading
8/15 Monday: Pave Binder

Donnelly Cross Rd
8/15 Monday: Reclaim and Grade
8/16 Tuesday: Pave Binder

Brooks Pond Cross Rd
8/16 Tuesday: Pave Top

Northwest Rd
8/17 Wednesday: Start top Northwest Rd or Paxton Rd if structures are done and its ready for top
8/18 Thursday: Complete top on Northwest Rd or Paxton Rd if ready.